What is the cycle time per day in the unit of second


Discuss the below in detail:

Q: Given the following manufacturing precedence relationships and assuming eight working hours a day and 310 products need to be produced per day.

Task

Description

Task Time (seconds)

Preceding Task

A

Punching

16


B

Bending

22

A

C

Combining

17

B

D

Painting

34

C

E

Polishing

35

D

What is the cycle time per day in the unit of second?