Q: Given the following manufacturing precedence relationships and assuming eight working hours a day and 310 products need to be produced per day.
Task
|
Description
|
Task Time (seconds)
|
Preceding Task
|
A
|
Punching
|
16
|
|
B
|
Bending
|
22
|
A
|
C
|
Combining
|
17
|
B
|
D
|
Painting
|
34
|
C
|
E
|
Polishing
|
35
|
D
|
What is the cycle time per day in the unit of second?