You have a machine that is staffed 8 hours per day. The average throughput rate is 28 batches per day, and the setup time is 5 minutes per batch. The plant operates 16 hours per day.
i. What is the Cycle Time per batch?
ii. What is the average processing time per batch?
For a batch size of 20 units, calculate
i. Average processing time per unit
ii. MTT per unit