What is the critical path what is the expected project


The following represents a project that should be scheduled using CPM:

Activity   Immediate Predecessors Times(days)

                                                 a      m      b

A                     -                    1    3    5           

B                    -                      1            2     3

C                     A                    1            2     3

D                     A                    2            3     4

E                    B                    3              4    11

F                     C,D                3              4     5

G                     D,E                1             4      6

H                     F,G                 2             4      5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?