Project Problem
Given the following information, answer the questions about this project: ActivityExpected DurationPredecessors
• Draw the network as a Gantt chart.
• What is the critical path? Which activities have slack time?
• What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?
The response must include a reference list. Using one-inch margins, double-space, Times New Roman 12 pnt font and APA style of writing and citations.