Assignment:
Intel is designing a new microprocessor and they want to build a prototype. The activities necessary to build the prototype are given in this table below. What is the critical path? How many weeks will it take to build the prototype, assuming normal cost? Draw the project schedule and fill in the numbers, per the Activity Format shown below. How much will it cost to crash the project to 11 weeks?