Problem: MRP planned receipts for item BB are calculated using the Silver-Meal Heuristic. The Net Requirements for the next three weeks are 73, 90, and 54. The order cost is $21 and the holding cost rate is $ 0.22 /week. What is the Cost/Period if all three requirements are added for single PR order? 2 decimal places in $