The ledger of Custer Company has the following work in process account.
Work in Process-Painting
5/1 Balance 3,720 5/31 Transferred out ?
5/31 Materials 6,560
5/31 Labor 4,640
5/31 Overhead 2,240
5/31 Balance ?
Production records show that there were 560 units in the beginning inventory, 30% complete, 1,540 units started, and 1,490 units transferred out. The beginning work in process had materials cost of $2,350 and conversion costs of $1,370. The units in ending inventory were 40% complete. Materials are entered at the beginning of the painting process.
(a) How many units are in process at May 31?
(b) What is the unit materials cost for May?
(c) What is the unit conversion cost for May?
(d) What is the total cost of units transferred out in May?
(e) What is the cost of the May 31 inventory?