The CHEETAH program has an RDT&E-funded project scheduled to start in November 2015 which is expected to take 21 months to complete. The project is expected to cost a total of $21 million (then-year dollars), with cost expected to be incurred at a rate of $1 million per month. What is the correct amount to include in the budget request for this project?
A. $12 million for FY 2015 and $9 million for FY 2016
B. $11 million for FY 2016 and $10 million for FY 2017
C. $11 million for FY 2015 and $10 million for FY 2016
D. $12 million for FY 2016 and $10 million for FY 2017