Olin Transmissions, Inc., has the following estimates for its new gear assembly project price- $134 per unit; variable costs-$30 per unit; fixed costs-$41329; quantity-6830 units. Suppose the company believes all of its estimates are accurate only within +/-17 percent. What is the company's EBIT when it performs its best-case scenario analysis? (Round your final answer to the nearest dollar amount. Omit the "$" sign and commas in your response. For example, $123,456.78 should be entered as 123457.)