For project A, the cash flow effect from the change in net working capital is expected to be 500 dollars at time 2, the level of net working capital is expected to be 600 dollars at time 0, and the level of net working capital is expected to be 2,000 dollars at time 2. What is the cash flow effect from the change in net working capital expected to be at time 1?