Problem
Consider the following batch flow process consisting of three process steps performed by three machines.
|
Step 1
|
Step 2
|
Step 3
|
Processing time
|
2 mins/unit
|
3 mins/unit
|
1.5 mins/unit
|
Setup Time
|
20 mins
|
No setup
|
No setup
|
a) Assume that the batch size is 10 parts. What is the capacity of the process?
b) For a batch size of 50 parts, which step is the bottleneck for the process?
c) What is the ideal batch size (i.e. one that minimizes inventory without affecting process capacity)?