JB Electronics produces a critical component used in many consumer products. Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line. Each worker must perform at least one task. There is unlimited demand.
Task
|
Time to complete task( seconds)
|
1
|
30
|
2
|
25
|
3
|
15
|
4
|
20
|
5
|
15
|
6
|
20
|
7
|
50
|
8
|
15
|
9
|
20
|
10
|
25
|
11
|
15
|
12
|
20
|
The current conveyor-paced assembly-line configuration assigns the workers in the following way
Worker 1: Tasks 1, 2, 3
Worker 2: Tasks 4, 5, 6
Worker 3: Tasks 7, 8, 9
Worker 4: Tasks 10, 11, 12
1. What is the capacity of the current line?
2. What are the throughput time and the average WIP inventory?