The amusement part is trying to develop some metrics. The park opens at 9 am. The gates close at 6 pm so no new customers can enter. Customers arrive at a continuous rate of 560 per hour. Customers leave at a continuous rate of 420 per hour (and do not return), starting at 9 am also.
a. What is the average time a customer spends in the park?.