The following jobs are waiting to be processed at Rick Solans machine center. Solans machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day) compute all times based on initiating work on day 241
Job
|
Date received
|
Due date
|
Duration (days)
|
1
|
235
|
360
|
40
|
2
|
231
|
310
|
30
|
3
|
228
|
300
|
15
|
4
|
225
|
270
|
25
|
5
|
230
|
320
|
35
|
What is the average tardiness (job lateness) for the sequence using the FCFS rule?
The sequence is
Job
4
3
5
2
1