The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:
- Standard Costs
- Direct Labor 7,500 hours @ $12
- Actual Costs
- Direct Labor 7,400 hours @ $11.40
What is the amount of the direct labor time variance?