Activity rates from Quattrone Corporation's activity-based costing system are listed below.
The company uses the activity rates to assign overhead costs to products:
Activity Cost Pools Activity Rate Processing Cutomer Orders 92.86
Assembling Products 1.78
Setting Up Batches 52.09
Last year, Product F76D involved 2 customer orders, 434 assembly hours, and 20 batches.
How much overhead cost would be assigned to Product F76D using the activity-based costing system?