What is project costs between the earliest completion time


Assignment:

You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,800 per week, and penalty costs are $600 per week after week 12.

2052_P 4.jpg

a. What is the minimum-cost schedule for this project?

b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part (a)?

Request for Solution File

Ask an Expert for Answer!!
Financial Management: What is project costs between the earliest completion time
Reference No:- TGS02099811

Expected delivery within 24 Hours