Problem
Each person needs to be able to read data charts and graphs with risk data. Go to the article by Kendrick (2008) uploaded in Content, Session for this exam. Locate the Pareto chart, which demonstrates "frequency/most often occurring" risks. He identified 270 projects with scope risks and 197 with schedule risks. What is the number of Weeks of Project Impact for those schedule risks, per the Pareto chart? What is the "average impact in weeks" for risks due to inadequate schedule estimates of activities?