Question: Nathan Factory manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer, an average of 50 days. This 50 day is spent as follows: Wait time 10 days Move time 5 days Process time 20 days Queue time 15 days Inspection time 5 days What is Nathan Factory's manufacturing cycle efficiency (MCE) for its snowmobiles? Group of answer choices 40% 44.4% 30% 37.5%

 