What is hitechs pool rate for the automated machinery


HiTech Products manufactures three types of remote-control devices: Economy, Standard, and Deluxe. The company, which uses activity-based costing, has identified five activities (and related cost drivers). Each activity, its budgeted cost, and related cost driver is identified below.

Activity Cost Cost Driver
  Material handling $277,000      Number of parts
  Material insertion 3,270,000      Number of parts
  Automated machinery 874,000      Machine hours
  Finishing 197,000      Direct labor hours
  Packaging 197,000      Orders shipped
           
  Total $4,815,000        
       

The following information pertains to the three product lines for next year:

   Economy Standard Deluxe
  Units to be produced 19,400    8,700     2,000    
  Orders to be shipped 1,130    760     285    
  Number of parts per unit 10    20     30    
  Machine hours per unit 1    3     6    
  Labor hours per unit 2    2     2    

1.     Required information   What is HiTech's pool rate for the material-handling activity closest to?

$9.19 per part. A rate other than those listed above. $0.65 per part. $1.43 per part. $4.60 per labor hour.

2.     Required information   What is HiTech's pool rate for the automated machinery activity closest to?

$15.70 per labor hour. A rate other than those listed above. $52.42 per unit. $15.20 per machine hour. $51.00 per machine hour.

3.     Required information   What is HiTech's pool rate for the finishing activity closest to?

$3.27 per machine hour. A rate other than those listed above. $3.27 per unit. $3.27 per labor hour. $5.77 per unit.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is hitechs pool rate for the automated machinery
Reference No:- TGS02549028