What is critical path and which activities have slack time


Problem

Given the following information, answer the questions about this project: ActivityExpected DurationPredecessorsA4 days-B9 daysAC11 daysAD5 daysBE3 daysBF7 daysCG3 daysD, FH2 daysE, GI1 dayH

• Draw the network as a Gantt chart.

• What is the critical path? Which activities have slack time?

• What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?

The response should include a reference list. Using one-inch margins, Times New Roman 12 pnt font, double-space and APA style of writing and citations.a

Solution Preview :

Prepared by a verified Expert
Management Information Sys: What is critical path and which activities have slack time
Reference No:- TGS03124852

Now Priced at $20 (50% Discount)

Recommended (90%)

Rated (4.3/5)