What is cost and schedule variance


Assignment:

Question 1. Assume you have completed three months of the project. The BAC was $200 000 for this six month project. Also assume the following:

PV = $120,000
EV = $100,000
AC = $90,000

a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
 
c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Solution Preview :

Prepared by a verified Expert
Basic Statistics: What is cost and schedule variance
Reference No:- TGS01849495

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)