Problem: The following data relate to the Tori Company for May and August: May August Maintenance hours 20,000 25,000 Maintenance cost $ 1,322,000 $ 1,417,000 May and August were the lowest and highest activity levels, and Tori uses the high-low method to analyze cost behavior. If maintenance hours are estimated to be 23,000 hours in October, then: