Question 1. Complete the level production plan using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here.
Information |
Lay off |
Hiring |
Inventory |
Totals: |
25 |
25 |
27,690 |
Costs: |
$112,500 |
$87,500 |
$166,140 |
Cost of plan: |
|
$366,140 |
|
Planning values |
|
|
|
Starting inventory: |
|
|
1,000 |
Starting and ending workforce: |
|
|
227 |
Hours worked per month per worker: |
|
|
160 |
Hours per unit: |
|
|
20 |
Hiring cost per worker: |
|
|
$3,500 |
Layoff cost per worker: |
|
|
$4.50 |
Monthly per-unit holding cost: |
|
|
$6 |
MONTH |
FORECASTED SALES |
SALES IN WORKER HOURS |
WORKERS NEEDED TO MEET SALES AVERAGE = 252 |
ACTUAL WORKERS |
ACTUAL PRODUCTION |
LAYOFFS |
HIRINGS |
ENDING INVENTORY |
March |
1,690 |
|
|
|
|
|
|
|
|
April |
1,350 |
|
|
|
|
|
|
|
|
May |
1,240 |
|
|
|
|
|
|
|
|
June |
1,300 |
|
|
|
|
|
|
|
|
July |
1,504 |
|
|
|
|
|
|
|
|
August |
1,992 |
|
|
|
|
|
|
|
|
September |
2,504 |
|
|
|
|
|
|
|
|
October |
2,504 |
|
|
|
|
|
|
|
|
November |
3,200 |
|
|
|
|
|
|
|
|
December |
3,000 |
|
|
|
|
|
|
|
|
January |
2,504 |
|
|
|
|
|
|
|
|
February |
2,000 |
|
|
|
|
|
|
|
|
Question 2. Complete the chase production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plan correctly, your hiring, layoff, and inventory costs should match those given here.
|
LAYOFF |
HIRING |
INVENTORY |
Totals: |
250 |
250 |
12,000 |
Costs: |
$500,000 |
$750,000 |
$72,000 |
Cost of plan: |
|
$1,322,000 |
|
Planning values |
|
|
|
Starting inventory: |
|
|
1,000 |
Starting and ending workforce: Hours |
|
|
227 |
worked per month per worker: |
|
|
160 |
Hours per unit: |
|
|
20 |
Hiring cost per worker: |
|
|
$3,000 |
Layoff cost per worker: |
|
|
$2,000 |
Monthly per-unit holding cost: |
|
|
$6 |
MONTH |
FORECASTED SALES |
SALES IN WORKER HOURS |
WORKERS NEEDED TO MEET SALES AVERAGE = 252 |
ACTUAL WORKERS |
ACTUAL PRODUCTION |
LAYOFFS |
HIRINGS |
ENDING INVENTORY |
March |
1,592 |
|
|
|
|
|
|
|
|
April |
1,400 |
|
|
|
|
|
|
|
|
May |
1,200 |
|
|
|
|
|
|
|
|
June |
1,000 |
|
|
|
|
|
|
|
|
July |
1,504 |
|
|
|
|
|
|
|
|
August |
1,992 |
|
|
|
|
|
|
|
|
September |
2,504 |
|
|
|
|
|
|
|
|
October |
2,504 |
|
|
|
|
|
|
|
|
November |
3,000 |
|
|
|
|
|
|
|
|
December |
3,000 |
|
|
|
|
|
|
|
|
January |
2,504 |
|
|
|
|
|
|
|
|
February |
1,992 |
|
|
|
|
|
|
|
|
Question 3. The manufacturer of TricoFlexers has agreed to offer Pam a price discount of $5 per unit ($45 rather than $50) if she buys 1,500. Assuming that annual demand is still 40,000, how many units should Pam order at a time?
Question 4. Jimmy's Delicatessen sells large tins of Tom Tucker's Toffee. The deli uses a periodic review system, checking inventory levels every 8 days, at which time an order is placed for more tins. Order lead time is 2 days. Average daily demand is 7 tins, so average demand during the reorder period and order lead time (10 days) is 70 tins. The standard deviation of demand during this same 10-day period is 17 tins. Calculate the restocking level. Assume that the desired service level is 95%.
Question 5. For problem 4, suppose that the standard deviation of demand during the 10-day period drops to 4 tins. What happens to the restocking level? Explain why.
Question 6. For Tom Tucker's Toffee in problem 4, draw a saw-tooth diagram similar to the one in Figure 11.3. Assume that the beginning inventory level is equal to the restocking level and that the demand rate is a constant 7 tins per day.
What is the safety stock level?
What is the average inventory level?
Question 7. The lead time for KraftyCity workbenches is 4 weeks, with a standard deviation of 1.5 weeks, and the average weekly demand is 20, with a standard deviation of 7 work-benches. What should the reorder point be if KraftyCity wants to provide a 95% service level?
Question 8. Now suppose the supplier of workbenches guarantees KraftyCity that the lead time will be a constant 4 weeks with no variability (i.e., standard deviation of lead time = 0). Recalculate the reorder point, using the demand and service level information in problem 7. Is the reorder point higher or lower? Explain why.
Question 9. Consider the following partially completed master schedule record:
On-hand inventory at end of April: 40 |
Month |
May |
June |
|
Week |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
Forecasted demand |
210 |
210 |
210 |
230 |
225 |
230 |
210 |
210 |
Booked orders |
210 |
207 |
209 |
200 |
200 |
187 |
132 |
185 |
Projected ending inventory |
|
|
|
|
|
|
|
|
Master production schedule |
600 |
|
|
675 |
|
|
600 |
|
Available to promise |
|
|
|
|
|
|
283 |
|
a. Complete the projected on-hand inventory calculations and the available-to-promise calculations.
b. Suppose that a customer calls and cancels an order for 50 units in week 25. Which of the following statements are true?
- The ATP for week 25 will increase by 50 units.
- The projected ending inventory for week 25 will remain the same.
- The ATP for weeks 19 and 22 will be affected.
Question 10. Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown.
WEEK |
|
1 |
2 |
3 |
4 |
5 |
6 |
***A2*** |
Gross requirments |
300 |
300 |
300 |
200 |
250 |
250 |
LT(weeks) = 2 |
Scheduled receipts |
|
260 |
|
|
|
|
|
Projected ending inventory:360 |
|
|
|
|
|
|
|
Net requirements |
|
|
|
|
|
|
Min. order = 1 |
Planned receipts |
|
|
|
|
|
|
|
Planned orders |
|
|
|
|
|
|
Question 11. Now suppose the lead time for item A2, shown in problem 6, is three weeks rather than two weeks. Based on this information, can the company support the current gross requirements for the A2? Why? What are the implications of having reliable supplier and manufacturing lead times in an MRP environment?
Question 12. Republic Tool and Manufacturing Company of Carlsbad, California, make a wide variety of lawn care products. One of Republic's products is the Model Number 540 Broadcast Spreader:
Complete the following MRP records. Note the following:
- Republic intends to start assembling 2,000 broadcast spreader kits in weeks 2, 4, and 6.
- The gross requirements for the gear and rotor plate assembly have already been given to you. For the remaining items, you will need to figure out the gross requirements.
- All scheduled receipts, lead times, and beginning inventory levels are shown.
- Note that cotter pins appear twice in the bill of material.
Gear and rotor plate assembly: Lead time = 1 week; Minimum order quantity = 2500
WEEK |
1 |
2 |
3 |
4 |
5 |
6 |
Gross requirments |
|
2,000 |
|
2,000 |
|
2,000 |
Scheduled receipts |
|
|
|
|
|
|
Projected ending inventory:1000 |
|
|
|
|
|
|
Net requirements |
|
|
|
|
|
|
Planned receipts |
|
|
|
|
|
|
Planned orders |
|
|
|
|
|
|