Problem
Read the Casa De Paz Development Project case study found at the end of chapters 1 through 5, CPM 4e and answer the following questions in a paper formatted using a question-response format:
If you were the project manager, what expertise would you like from the sponsor, stakeholders, or core team members to create a milestone schedule with acceptance criteria? Minimum 250 words.