Question: After speaking with the VP of Information Technology department (a key stakeholder of the project), the PM included a special condition for the sellers. The winning supplier will not be allowed to subcontract sections of the scope of work to third parties. What element of planning procurements is addressed by the PM? Contract payment types Procurement phases Delivery methods Make-or-buy decisions