What do you infer about the project schedule and cost


Problem

A project is scheduled to complete in six months duration. There are two activities in the project. The actual cost of Activity 1 is SAR 300,000 and that of Activity 2 is SAR 200,000. The planned value of these activities is SAR 280,000 and 150,000 respectively. On reviewing, the current project status is Activity 1 is 100% completed and Activity 2 is only 75% completed.

• Perform the earned value calculations of the above project scenario and fill the given table.
• What do you infer about the project schedule and cost based on your calculations?