1. The critical path of a project has an expected duration of 43 days and a standard deviation of 7.6 days. Suppose we have to promise a completion date for this project that has only a 2.5% chance of being exceeded. What would we promise?

2. What do airlines use to Market and Brand their product?

3. A given project's critical path has an expected duration of 63 days, with a standard deviation of 2 days. What is the probability that this project will take longer than 63.1 days?