In a job shop, effective capacity is only 72 percent of design capacity, and actual output is 84 percent of effective output. What design capacity would be needed to achieve an actual output of 16 jobs per week? What is its effective capacity?
a. The Design Capacity needed to achieve the required actual job outputs = (round to whole number)
b. The Effective Capacity needed to achieve the required actual job outputs = (round to whole number)