What cycle time would match capacity and demand if demand is 167 units a day, there are 1 shift(s) of 452 minutes each, and workers are given three 45 minute breaks during each shift, one of which is for lunch or dinner? (Round your answer to 2 decimal places.)
Cycle time minutes per cycle