Question:
Overhead Variances
Three Bridges, Inc., shows the following overhead information for the current period:
Actual overhead incurred
|
$638,400 ($182,400 fixed and $456,000 variable)
|
Budgeted fixed overhead
|
$187,200 (12,000 direct labor-hours budgeted)
|
Standard variable overhead rate
|
|
per direct labor-hour
|
$36
|
Standard hours allowed for
|
|
actual production
|
14,000 hours
|
Actual labor-hours used
|
13,200 hours
|
Required
What are the variable overhead price and efficiency variances and the fixed overhead price variance?