The following information is available pertaining to Bonita Division, who uses a plant-wide overhead rate on machine hours:
- Mixing Dept Finishing Dept Total
- Overhead $30,000 $60,000 $90,000
- Direct labor hours 7,500 2,500 10,000
- Machine hours 2,500 7,500 10,000
Production information pertaining to Job 101:
- Mixing Dept Finishing Dept Total
- Prime costs $5,000 $0 $5,000
- Direct labor hours 250 0 250
- Machine hours 10 10 20
- Units produced 500 0 500
What are the total overhead costs assigned to Job 101?