What are the total normal costs for the project


Question:

Bob Summers, CEO of Summer Construction has an opportunity to bid on a contract that pays $5500 upon completion, but the contract calls for a late performance penalty of $140 per week for each week that the project is delayed beyond eight weeks.

Activity    Normal Time    Normal Cost    Crash Time    Crash Cost    Immediate Predecessors
A    1    $300    1    $300    -
B    3    $400    1    $470    A
C    2    $350    1    $550    A
D    5    $550    4    $675    A
E    4    $300    3    $375    C
F    2    $450    1    $500    C
G    7    $425    5    $525    C
H    4    $525    2    $625    B,E
I    3    $250    1    $330    D,F
J    1    $300    1    $300 H,G,I

A. Find the crash cost per week for each activity and record the results in the crash table in the table. What are the total normal costs for the project?

B. Which activity would you recommend that Hank crash first, if any?

C. What project duration will minimize project cost?

D. What is the maximum profit that Summers can attain for this project?

Solution Preview :

Prepared by a verified Expert
Project Management: What are the total normal costs for the project
Reference No:- TGS01954871

Now Priced at $25 (50% Discount)

Recommended (99%)

Rated (4.3/5)