Problem: The three elements of risk are: a. Enterprise risk, project management risk, and financial risk. b. The problem associated, the consequences, and the corrective action that needs to be implemented to resolve. c. The likelihood or probability of occurrence, the impact or consequences that occurs from risk, and the priority or importance of the risk. d. All of the above is correct e. None of the above is correct