A project has just completed the 80th item in its action plan of 100. It was scheduled to have spent $178,000 at this point in the plan, but has actually spent only $165,000. The foreman estimates that the value of the work performed is about $170,000. What are the spending and schedule variances for the project? What are the SPI & CPI in this example?