A petrochemical mixing facility pays $0.07 per kWh for electric energy, and $6.66 per kW/mo for peak electrical demand. The facility also has a ratchet clause, where the facility is charged either: 80% of their highest demand peak for the last 12 months, or 100% of the current month's peak demand, whichever is greater.
The peak demand (in kW) for the last 12 months is:
Jan.  Feb.  Mar.   Apr.  May  June  July   Aug.  Sept.  Oct.  Nov.  Dec.
900  735    680   695   740   720    710   650    660    690   685   710
Once a year in January, the facility tests their large fire suppression system pump during the afternoon, by running them at full load for 4 hours.
The pump size 300hp (224 kW).
What are the estimated cost savings by scheduling the tests to be run by at night, when no production processes are occurring