Problem:
A project has the following activities, precedence relationships, and time estimates in days:
Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6
Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity
What are the critical path and duration of the project?
What is the probability that the project will take longer than 38 days?