What are baseline dates based on 2 what is variance and how


Session 5.1 Quick Check 1. What are baseline dates based on? 2. What is variance, and how is it calculated? 3. What do positive and negative variance indicate? 4. What table do you apply to the task sheet to see baseline dates? What table do you apply to see actual dates? What table do you apply to enter actual fixed costs? 5. Identify three methods that you can use to track and update progress on a task. 6. When you update tasks that are on schedule or reschedule tasks that are behind schedule, what date is used to determine which tasks should be updated or rescheduled?  

Request for Solution File

Ask an Expert for Answer!!
Project Management: What are baseline dates based on 2 what is variance and how
Reference No:- TGS01186245

Expected delivery within 24 Hours