Question 1:
Analyze and explain this idea: How does multitasking make it difficult to accurately resource-level a project?
Your response should be at least 200 words in length.
Question 2:
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
Your response should be at least 200 words in length.