What amount should mill recognize as gross profit


Mill Construction Co. uses the percentage-of-completion method of accounting. During 1996, Mill contracted to build an apartment complex for Drew for $20,000,000. Mill estimated that total costs would amount to $16,000,000 over the period of construction. In connection with this contract, Mill incurred $2,000,000 of construction costs during 1996. Mill billed and collected $3,000,000 from Drew in 1996. What amount should Mill recognize as gross profit for 1996?

a. $250,000
b. $375,000
c .$500,000
d. $600,000

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What amount should mill recognize as gross profit
Reference No:- TGS055549

Expected delivery within 24 Hours