Westside auto builds automobile generator .they contract with case casting to supply case for the generators and build the rest of the product in-house. West side’s operation runs at a constant rate and requires 1000 cases per month throughout the year, assume the ordering costs are $25 per order and annual holding costs are fifty cents per generator case. Westside has 250 working days per year and a lead time of 5 days
what is the EOQ for generator cases?
what is the reorder point?
what is the cycle time?
what is the total annual cost of ordering and holding generator cases?