Westin watercrafts predetermined overhead rate for year


Question: Westin Watercraft's predetermined overhead rate for year 2011 is 200% of direct labor. Information on the company's production activities during May 2011 follows.

a. Purchased raw materials on credit, $125,000.

b. Paid $84,000 cash for factory wages.

c. Paid $11,000 cash to a computer consultant to reprogram factory equipment.

d. Materials requisitions record use of the following materials for the month.

Job 136 . . . . . . . . . . . . . . . . . . . . $30,000

Job 137 . . . . . . . . . . . . . . . . . . . . 20,000

Job 138 . . . . . . . . . . . . . . . . . . . . 12,000

Job 139 . . . . . . . . . . . . . . . . . . . . 14,000

Job 140 . . . . . . . . . . . . . . . . . . . . 4,000

Total direct materials . . . . . . . . . 80,000

Indirect materials . . . . . . . . . . . . 12,000

Total materials used . . . . . . . . . . $92,000

e. Time tickets record use of the following labor for the month.

Job 136 . . . . . . . . . . . . . . . . $ 8,000

Job 137 . . . . . . . . . . . . . . . . 7,000

Job 138 . . . . . . . . . . . . . . . . 25,000

Job 139 . . . . . . . . . . . . . . . . 26,000

Job 140 . . . . . . . . . . . . . . . . 2,000

Total direct labor . . . . . . . . 68,000

Indirect labor . . . . . . . . . . . . 16,000

Total . . . . . . . . . . . . . . . . . . . $84,000

f. Applied overhead to Jobs 136, 138, and 139.

g. Transferred Jobs 136, 138, and 139 to Finished Goods.

h. Sold Jobs 136 and 138 on credit at a total price of $340,000.

i. The company incurred the following overhead costs during the month (credit Prepaid Insurance for expired factory insurance).

Depreciation of factory building . . . . . . . . . . . $37,000

Depreciation of factory equipment . . . . . . . . 21,000

Expired factory insurance . . . . . . . . . . . . . . . . 7,000

Accrued property taxes payable . . . . . . . . . . . 31,000

j. Applied overhead at month-end to the Goods in Process (Jobs 137 and 140) using the predetermined overhead rate of 200% of direct labor cost.

Required: 1. Prepare a job cost sheet for each job worked on during the month. Use the following simplified form.

2276_Job No..png

2. Prepare journal entries to record the events and transactions a through j.

3. Set up T-accounts for each of the following general ledger accounts, each of which started the month with a zero balance: Raw Materials Inventory; Goods in Process Inventory; Finished Goods Inventory; Factory Payroll; Factory Overhead; Cost of Goods Sold. Then post the journal entries to these T-accounts and determine the balance of each account.

4. Prepare a report showing the total cost of each job in process and prove that the sum of their costs equals the Goods in Process Inventory account balance. Prepare similar reports for Finished Goods Inventory and Cost of Goods Sold.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Westin watercrafts predetermined overhead rate for year
Reference No:- TGS02332039

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)