Wells contracted with the state to erect a building according to the state's specifications and to lease it to the state. Time was made of the essence in the contact. Wells completed the building two months late. The state cancelled the contract and leased space elsewhere. Wells sued and proved at trial that the delay was caused by the state’s failure to indicate locations for electrical fixtures, outlets, and other details as required by the contract. Did Wells win? Why or why not?