Problem 1: The table which is given below depicts the WBS Dictionary for software development project:
Task1. Using any appropriate technique, calculate the duration of the project.
Task2. Describe the resource requirements for the project (specify when each resource is required)
Task3. Comment on resource usage in this project and suggest improvements that could be done as far as resource usage is concerned in this company. State any assumptions.
Task4. It is suggested to the customer that his tasks are not optimally organized and that fast tracking the project should be envisaged. How could the project be fast tracked?
Task5. What would be the new project duration with the recommended fast tracking strategy?
Task6. What is the impact on resource usage with fast tracking?
Task7. What are the dangers of fast tracking?