--%>

Wat is the critical path for the project how much slack


Microsoft Project Assignment

MS Project 2013 experience required

This assignment consists of two parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule

(Submit as one Microsoft Project file)

1. Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints.

Note: When you create your MS Project schedule, you will need to update your project per the following constraints:

o The project must consist of at least twenty (20) tasks.
o Each task must have a start and finish date that matches the duration noted in the assignment.
o Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew).
o Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).
o In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

(Submit as a Microsoft Word file)

1. Respond to the following questions in a one to two page paper based on your project schedule.

o When will the project be completed?
o What is the critical path for the project?
o How much slack / float is in your project? What activities have the greatest slack / float?
o Identify the top three activities that you believe could impact the project completion date.
o What additional activities you would add to this project to make it more complete, from a project management viewpoint?

Greendale Stadium Case:

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said that if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball park with modern lluxury boxes.

Use Table 6.3 to construct a network schedule for the stadium project:

Greendale Stadium Case

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

 

 

2

Clear stadium site

70 days

-

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

2

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

3,6

8

Install playing field

90 days

3,6

9

Construct upper steel bowl

120 days

3,6

10

Install seats

140 days

7,9

11

Build luxury boxes

90 days

7,9

12

Install jumbotron

30 days

7,9

13

Stadium infrastructure

120 days

7,9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

14

16

Build roof supports

90 days

6

17

Construct roof

180 days

16

18

Install roof tracks

90 days

16

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19

Solution Preview :

Prepared by a verified Expert
Project Management: Wat is the critical path for the project how much slack
Reference No:- TGS01695847

Now Priced at $45 (50% Discount)

Recommended (95%)

Rated (4.7/5)