Warr Company is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC or negative, in both cases it will be rejected. Year 0 1 2 3 4 Cash flows -$1,575 $400 $400 $400 $400 (Points : 10) 0.61% 0.53% 0.63% 0.51% 0.62%