Which activity shorten to decrease project duration


Design project network from information given below:

Activity Predecessor Duration
a none 2
b a 4
c a 3
d a 2
e b 3
f c 6
g c d 5
h e f 6
i g 5
j h i 5

Activities b and h can be shortened to minimum of 2 weeks. Which activity would you shorten to decrease project duration by 2 weeks? WHY? Illustrate critical path.