Vehicles arrive at a freeway on-ramp meter at a constant rate of six per minute starting at 6:00A.M. Service begins at 6:00A.M. such that u(t)=2+0.5t, where u(t) is in veh/min and t is in minutes after 6:00A.M. What is the total delay and the maximum queue length?