Problem: Adelphi Fabrics Corporation manufactured 500 units of a special multilayer fabric with the trade name Stylex during July. The following information from the Stylex production department pertains to July:
Direct material purchased: 18,000 yards at $1.38 per yard
|
$24,840
|
Direct material used: 9,500 yards at $1.38 per yard
|
13,110
|
Direct labor used: 2,100 hours at $9.15 per hour
|
19,215
|
The standard prime costs for one unit of Stylex are:
Required:
Direct material: 20 yards at $1.35 per yard
|
$27
|
Direct labor: 4 hours at $9.00 per hour
|
36
|
Total standard prime cost per unit of output
|
$63
|
Compute the following variances for the month of July, indicating whether each variance is favorable or unfavorable.
a. Direct-material price variance.
b. Direct-material quantity variance.
c. Direct-labor rate variance.
d. Direct-labor efficiency variance.