Problem:
A firm is reviewing a project with labor cost of $6.00 per unit, raw materials cost of $22.25 a unit, and fixed costs of $10,000 a month. Sales are projected at 8,000 units over the 3-month life of the project.
Required:
Question: What are the total variable costs of the project?
Note: Please show how to work it out.